How Long Does a Kitchen Remodel Really Take?

Remodeling your kitchen can be an exciting project that transforms your home. But before you start demolition, it’s important to set realistic expectations when it comes to timelines.

A kitchen remodel is a complex process with many moving parts. The total timeline can range from 6-12 weeks for a full renovation. To stay on track, it’s crucial to understand how long each phase takes.

The 4 Main Phases of a Kitchen Remodel

A kitchen remodel consists of four key phases:

average kitchen remodel time

The construction phase is the longest, while demo is the quickest. Let’s examine what’s involved in each stage.

Phase 1: Design

The design process takes 2-4 weeks. This involves:

A designer can help you optimize and visualize your new kitchen. Allow plenty of time for making decisions and getting permits approved.

Phase 2: Demolition

Demolition is the quickest phase, usually lasting 1-3 days. This involves:

Have a dumpster ready for all the debris. Demolition creates a lot of dust and noise but goes quickly with a professional crew.

Phase 3: Construction

The construction phase is the longest and most complex stage of a kitchen remodel. It involves:

A general contractor will coordinate all the various trades to complete their work. Expect the construction phase to take 4-10 weeks depending on scope.

Phase 4: Finishing Touches

Finishing touches take about 1 week. This final phase includes:

At the end, you’ll have a stunning, brand new kitchen ready to enjoy and host in.

How Long Each Task Takes During Construction

Now let’s zoom in on the construction timeline. Here’s a rough estimate of how long each task takes:

There will likely be some overlap between these jobs. Your contractor will sequence the work efficiently so trades aren’t tripping over each other.

Ways to Shorten Your Timeline

If you’re eager to finish your remodel quickly, here are some tips:

Rushing comes with more stress and higher costs. But you may be able to shave off 1-2 weeks with careful planning.

How Weather Can Impact Your Timeline

Inclement weather can delay a kitchen remodel. If it’s extremely cold, icy, or snowy, construction may halt temporarily. The same goes for sweltering hot temperatures.

To avoid weather delays, schedule your remodel during the temperate spring and fall seasons. Summer heat can slow plumbing and electrical work. Budget extra time for winter weather just in case.

Kitchen Remodel Costs

While budgets vary immensely, the national average for a major kitchen remodel is around $66,000. Luxury kitchens can easily exceed $125,000.

Key costs include:

Get quotes from a few general contractors to compare rates. And build in a 10-15% contingency fund in case of unexpected issues.

A kitchen remodel takes 6-12 weeks from start to finish. Careful planning and an experienced contractor help ensure an efficient timeline.

The construction phase is the longest at 4-10 weeks. Demolition goes quickly, while design and finishing touches take 1-4 weeks. Now you know what to expect for each stage of a kitchen renovation.